SECOND SMOK SYSTEM INTEGRATION SEMINAR


B.2.12.2 Task
Technical Support for Quality Supervision

B.2 Component
Monitoring, Forecasting and Warning System
Institute of Meteorology and Water Management
Dębe /Warsaw, 16th & 17th April 2003
SMOK





Content

  • Organisation of the Task
  • Scope of the Task B 2.12.2
  • Progress of the Task since the First Integration Seminar
  • Pending issues concerning integration of the Task
  • Questions





Organization of the Task

    Task B.2.12.2:
  • Objectives:
    TSQS for the whole B2 Component
  • Leaders on the part of IMGW:
    Roman Sk±pski – B2 Coordinator
    Jan Orłowski – TL B2I
    Jerzy Czechowicz – DTL B2I
  • Contractors:
    SOGREAH / Louis Berger Intl., National Weather Service, Sofrecom , CIS
    Project Director: Jean-Luc Rahuel , Deputy PD: Marc Erlich
    Project Team Leader: Krzystof Switalski





B.2.12.2: Organisation structure






Scope / Objectives

  • Strengthen IMGW institutional and human capacity to effectively and efficiently implement SMOK
  • Ensure the SMOK Project quality through appropriate supervision of implementation and delivery of the individual B2 tasks.





Specific Objectives

  • Technical co-ordination of a timely delivery of the individual system components
  • Technical supervision of the final delivery of SMOK system development tasks
  • Co-ordination of SMOK development with other Components of the Flood Recovery Project, notably B.1 and B.4
  • Co-ordination of the System with the similar systems operated by the neighbouring countries
  • Review of contractor plans and activities v. the entire system, i.e., ensure compatibility of all system components
  • Assessment of the potential to reduce the financial investment and operating costs without impacting the system performance
  • Quality Assurance of the entire system and its constituent parts





Progress of the Task since the 1st Integration Seminar

    TASK 1 - Technical Assistance to Management of Component B.2
  • B.2.7.2
  • B.2.7.4 C, D, E, F, G
  • B.2.8.2
}

Successfully completed
  • B.2.5.2
Provisionally completed *
  • B.2.3.2
Started
  • B.2.1.3, B.2.2.5
To be launched

    TASK 2 - Co-ordination and Integration of the system elements
  • B.2.4.2
Testing
  • B.2.9.2
Implementation ongoing

    TASK 3 - Technical supervision of the final delivery of SMOK
  • Assistance to preparation of final delivery procedures

    TASK 4 - Co-ordination of SMOK development with other Project Components
  • Co-ordination with B.1 component
  • Co-ordination with B.4 component
Successfully completed

    TASK 5 - Support to co-ordination of the system with systems operated by neighbouring countries
  • Co-ordination for ODRA river basin (2 meetings with CHMI)
  • Co-ordination for BUG, SAN, NAREW river basins

    TASK 6 - Economic Assessment of the System
  • Investigation of financial arrangements for O&M
  • Final economic assessment of recurrent costs

    TASK 7 - Support to raising Public Awareness of System implementation
  • Definition of communication means and policies - Internet & Intranet strategy
  • Implementation of communication plan - building IMGW image

    TASK 8 - Training
  • Definition of communication means and policies - Internet & Intranet strategy
  • Seminars, workshops and meetings (2 SSI, 1 workshop)

    TASK 9 - Support to Contractual and Financial Management of Component B2
  • Assisting the Institute in internal control of the on-going and future contracts according to Polish and WB regulations